EngiMetric Arena / Spot the Error

Review this cement order: the bags were rounded down

  • Spot the Error
  • Construction & QS
  • foundation
Competency Quantitative reasoning primary

What you should take away: Recognise that a bag count is a discrete purchase: a fractional requirement must be rounded up, not down.

The situation

What is happening

A 1:2:4 concrete mix at a water-cement ratio of 0.5 is batched at 1 m3. The mix calculator returns 316.8 kg of cement, or 6.336 bags of 50 kg. The site ordered six bags. Review the order.

Given

Scenario values with units
QuantityValueUnitNote
Cement : sand : aggregate 1 : 2 : 4 by volume Nominal mix proportions.
Water-cement ratio 0.5 by mass Batching assumption.
Batch volume 1 m3 One cubic metre of finished concrete.
Cement required 316.8 kg From the mix engine.
Bag size 50 kg Standard bag.

Assumptions this challenge makes

  • The mix proportions are by volume and the cement is measured by mass.
  • The bag mass is exactly 50 kg; real bag fill has a tolerance.
  • No site wastage is included in the 1 m3 batch.

Your call

Your answer

Which finding is the defensible review conclusion?

What this challenge does not establish

  • The mix proportions are nominal and by volume; a real mix design would be based on trial batches and material properties.
  • No allowance is made for bag-fill tolerance, moisture in the aggregates or site wastage.
  • The engine assumes the stated water-cement ratio is the batching target, not a maximum.