Design Ocean desalination with subsurface intake

Doheny Ocean Desalination Project

Dana Point, South Orange County, California · United States

A small-to-mid-size ocean desalination project in Dana Point designed around the California Ocean Plan’s preferred environmental approach: fully submerged subsurface slant wells for intake and blended brine discharge through an existing outfall. The Phase 1 design-build-operate contract was awarded in October 2024, with the facility scheduled to come online in 2029.

Design Capacity
≈ 20,000 m³/day (5 MGD)
Project Value
≈ USD 170 million (total capital budget)
Status
Design
Announced
2022
Expected Completion
2029
Client / Offtaker
South Coast Water District (SCWD)
EPC Contractor
J.R. Filanc Construction and ACCIONA (design-build-operate)
Design Consultant
Hazen
Technology
Seawater RO fed by subsurface slant wells
Country
United States
Region
Dana Point, South Orange County, California
Last Verified
2024-12-11

Why This Project Matters

Doheny is a useful case study in how modern intake and brine-management regulation shapes desalination plant design. Subsurface intakes largely avoid marine-life entrainment, while blending brine with treated effluent lowers discharge salinity — both are the environmental pattern most likely to be replicated in future U.S. ocean desalination projects.

Timeline

  1. Permitting under way

    Major permits adopted, including the NPDES discharge permit and coastal development approvals.

  2. Design-build-operate contract awarded

    SCWD awards the Phase 1 PDBOM contract to the Filanc / ACCIONA joint venture with Hazen.

  3. Facility online target

    Projected plant start-up per the district’s published schedule.

Verification & Sources

EngiMetric tracks project facts against public sources only. Every value above (capacity, value, parties, status, dates) is cited. Content last verified on 2024-12-11.