Stage 12 of 13 / Commissioning
Commission and verify
Define the tests that prove the installed system matches the design, and the measurements that would falsify it.
- Practitioner
- 13 stages
- 10 min
- Solar PV and electrical storage
After this stage you can
- Name the electrical and energy tests that prove the design.
- Set acceptance criteria before seeing the measurements.
- Explain why an as-built change requires a re-run of the model.
The engineering
Commissioning is not a visual inspection. It is a set of measurements with acceptance criteria: insulation resistance, polarity, open-circuit voltage per string, short-circuit current, earth continuity, inverter configuration, battery capacity test and a monitored energy balance.
The design predicts specific yield, self-consumption and unserved energy. Commissioning should compare measured values with those predictions and investigate a material gap instead of explaining it away. A performance ratio far below the screen is evidence of a problem, not weather noise.
Record the as-built configuration. If the installer changes a string length, a breaker or a dispatch setting, the report must be re-run. The commissioning checklist is deliberately a template: the project team owns the instruments, calibration and signed results.
EngiMetric / solar workbench
Your project, computed stage by stage
Loading the saved project state...
Preview screen. Inputs are saved in this browser only. Resource presets and tariffs are illustrative. Failed checks stay visible; a clean summary is not a stamped design.
Your deliverable for this stage
A commissioning checklist with acceptance criteria and a re-run trigger for as-built changes.
Stage assumptions, limits and sources
Assumptions
- Test instruments are calibrated and operated by competent personnel.
- Acceptance criteria are agreed with the client and the installer.
Constraints
- No measured test data is generated or stored by the workbench.
- No grid-code or utility commissioning witness procedure is included.
Limitations
- The checklist is not a commissioning method statement or a safety procedure.
- No performance guarantee, liquidated damages or long-term monitoring plan.
Review status
- Needs engineering review
- Professional review is required before publication or use as a design basis.