Stage 10 of 13 / Comparison
Compare PV and storage options
Re-run yield, dispatch and economics for several PV/BESS sizes and reject options that fail the stated boundary.
- Practitioner
- 13 stages
- 12 min
- Solar PV and electrical storage
After this stage you can
- Compare options on energy, self-sufficiency, cost and feasibility.
- Explain why an infeasible option must be rejected before its NPV is read.
- Choose a shortlist and state the non-financial criteria that remain.
The engineering
A scenario is not a spreadsheet tweak. Each option re-runs yield, dispatch and cash flow under the same resource, load, tariff and dispatch policy. That makes the table like-for-like and exposes options that look cheap only because they leave load unserved.
Feasibility is explicit. An off-grid option must meet the load within the stated screening allowance; a grid-connected option must have no unserved energy. A low NPV does not rescue an infeasible design, and the table says so.
Use the comparison to choose a shortlist, not to declare a winner. The decision still depends on resilience, space, procurement and risk appetite, which are not in the model.
EngiMetric / solar workbench
Your project, computed stage by stage
Loading the saved project state...
Preview screen. Inputs are saved in this browser only. Resource presets and tariffs are illustrative. Failed checks stay visible; a clean summary is not a stamped design.
Inputs and outputs
You own
- PV kWp, BESS kWh and configuration for each option
- The shared resource, load, tariff and dispatch policy
You produce
- Per-option PV yield, self-consumption/sufficiency, unserved energy and curtailment
- CAPEX, NPV, payback, LCOE and a feasibility verdict
Your deliverable for this stage
A scenario table with a feasibility verdict and a defended shortlist.
Stage assumptions, limits and sources
Assumptions
- All options share the same load, resource and dispatch policy.
- The DC/AC ratio follows the base design unless the PV size changes it.
Constraints
- The scenario list is fixed in the workbench; it is not an optimiser.
- Off-grid feasibility uses a 1 % unserved-energy screening allowance.
Limitations
- No multi-objective optimisation, genetic algorithm or probabilistic uncertainty.
- No land, structural or procurement constraints on the larger options.
Review status
- Needs engineering review
- Professional review is required before publication or use as a design basis.
Sources
Stage progress is stored in this browser only. The explanation and every limit on this page remain readable with JavaScript disabled; the calculators need it to run.
Stage kind: Comparison / Journey: solar-bess-screening / Stage: scenarios