Stage 1 of 14 / Introduction
Write the project brief and design basis
Fix the workload type, capacity target, availability objective, site conditions, utility status, water status and cost boundary before a single number is computed.
- Advanced
- 14 stages
- 15 min
- Mission-critical electrical and thermal systems
After this stage you can
- State the project type, IT target, rack target, availability objective and operational date.
- Separate owner requirements, design assumptions and unresolved site information.
- Explain why grid status and water availability belong in the design basis rather than in a later procurement note.
The engineering
A data-center study fails quietly when the brief mixes owner wishes with verified facts. The project type changes the rack density and load shape. The availability objective changes the topology and cost. Utility capacity, water availability and climate are site facts that must be evidenced, not assumed because a template says so.
This stage separates four kinds of information. Owner requirements are targets such as IT capacity and availability. Assumptions are planning values such as design ambient temperature. Missing information is recorded explicitly, including utility approval and water permits. Verified data is rare in a first-pass study, and the report never labels an assumption as verified.
The default project is a 4 MW mixed AI/HPC campus in a hot coastal climate. It is a teaching case. Every climate, grid, water and cost value must be replaced before a real decision.
EngiMetric / AI data-center workbench
One project, computed from rack to report
Loading the saved project state...
Preview screen. Inputs are saved in this browser only. Climate, grid, water and cost values are illustrative. Failed checks stay visible; a clean summary is not a stamped design and no Tier rating is claimed.
Your deliverable for this stage
A design basis paragraph and a saved project state that every later stage reuses.
Stage assumptions, limits and sources
Assumptions
- The learner owns the project target and the site status labels.
- Climate values are design assumptions until replaced by a design weather dataset.
- Grid capacity is a stated figure, not an approved interconnection.
Constraints
- The workbench is a screening model, not a bankable design or an investment case.
- One saved state feeds every stage and the exported report.
Limitations
- No utility study, title search, geotechnical investigation or permit review.
- No measured climate, water or grid data is bundled with the journey.
Review status
- Needs engineering review
- Professional review is required before publication or use as a design basis.
Sources
- Uptime Institute - Tier Standard overviewengineering org
- ASHRAE - Data Center Guidance and Datacom Seriesengineering org
- Open Compute Project - Data Center Facility projectengineering org
- NVIDIA - DGX SuperPOD reference architectureofficial docs
- U.S. Department of Energy - Data centers and serversgovernment
Stage progress is stored in this browser only. The explanation and every limit on this page remain readable with JavaScript disabled; the calculators need it to run.