Stage 13 of 15 / Comparison
Re-run the plant through scenarios
Compare demand, tariff, capacity, water recovery, renewable factor and delivery-window variants using full model re-runs.
- Advanced
- 15 stages
- 14 min
- Process and energy systems
After this stage you can
- Run the full scenario set from the current state.
- Distinguish a blocking failure from an open site-status warning.
- Name which scenario would be chosen only after professional review.
The engineering
Each scenario clones the saved state, applies one perturbation and rebuilds the entire model. Feasibility here means the blocking production, mass-closure, energy-balance, storage-coverage and LCOH checks pass. Grid-status and water-status warnings can still be open.
The list is fixed: base, demand ±20 %, electricity +30 %, stack capacity −20 %, recovery 60 %, renewable capacity factor at 75 % of base, and 24-hour delivery. It is not an optimiser.
Use the table to see which assumption moves mass, kWh/kg and cost together. Do not treat a feasible row as a selected design.
EngiMetric / green hydrogen educational workbench
Green Hydrogen Plant — Educational Screening Workbench
Loading the hydrogen project state...
Draft development workbench (noindex). Inputs are saved in this browser only. Calculations shown are screening/educational outputs from the existing model where implemented; missing or unsupported quantitative areas remain explicit. Completing stages records self-declared learning progress only — it is not quantitative engineering capability, not an OEM guarantee, and not industrial/project approval.
Stage
Inputs
Edit the screening inputs for this stage, then calculate. Values you enter are marked as user-entered in the local project state; defaults remain illustrative until replaced.
Screening results
Results come from the existing hydrogen screening model. Unsupported quantitative areas, missing evidence, and review requirements remain explicit; outputs are not certified design or approval decisions.
Process & balance context
This educational workbench presents stage-specific calculated outputs and limitations. Detailed interactive diagrams are not required for journey completion; use the stage results and assumptions panels to review boundaries, flows, energy, storage, and economics context.
Assumptions, limitations & review
Your deliverable for this stage
A scenario comparison table generated from complete model re-runs.
Stage assumptions, limits and sources
Assumptions
- Each scenario is a single focused change unless noted.
- Feasibility ignores non-blocking status checks such as unconfirmed grid.
Constraints
- The scenario list is fixed in the workbench.
Limitations
- No multi-variable optimisation or Monte Carlo.
Review status
- Needs engineering review
- Professional review is required before publication or use as a design basis.
Sources
- CIAAW - Standard Atomic Weightsstandards
- NIST Chemistry WebBook - Hydrogengovernment
- U.S. Department of Energy - Hydrogen Production: Electrolysisgovernment
- IEA - Global Hydrogen Review 2024, Hydrogen productionresearch institution
- IRENA - Electrolyser costsengineering org
Stage progress is stored in this browser only. The explanation and every limit on this page remain readable with JavaScript disabled; the calculators need it to run.